VW Battersea

 

Our three storey VW Battersea fit out project for Lookers Plc is progressing very well at present with up to 40 skilled people on site working together to meet our programme.

Internal partitions are very well advanced and the finished layout of the building is really starting to take shape.  Milestones for this month involve the installation of the escalators, completion of the Welcome Wall, commencement of the finishing trades with tilers due to commence next week, along with closing the ceiling grid as the M&E installation is moving rapidly.  The quality of the M&E installation is evident throughout.

Our talented site team continue to showcase a very well managed site, and are scoring highly on our own internal audits, Principal Designer audits and Considerate Constructors.

There is a fantastic effort being put in by all involved within MARTIN and also the sub-contractors working on the scheme with us.

 