Kerrs Tyres

MARTIN’s site at Kerr’s Tyre’s, Antrim, is progressing well. Currently, we have completed the steelwork treatment process which has been finished in a goosewing grey colour to match the cladding. Brickwork around the perimeter of the frame is also nearing completion. We have also made great strides in getting the new access road up to level ready for the first layer of surfacing including the kerbing and main drainage lines. Across the site, drainage installation is pushing along with two attenuation tanks due in the coming weeks along with a biodisc and two petrol interceptors.
Great work by the site team and our valued supply chain.

 

#buildingMARTIN